Introduction
My Project title is xpress 700 small parts cleaning and optimization of
the cleaning process. Our current cleaning plan for the tablet press xpress 700
is inconsistent and cleaning times on the xpress 700 are erratic. The small
parts cleaning times are not optional for the number of shift changeovers
happening. This inconsistent work flow is increasing the amount of time needed
to complete the cleaning cycle which is effecting targets being met. This
project if successful will develop a more logical, streamlined approach to the
cleaning cycle which will also result in monthly batch targets being
consistently met.
Step
1 Define the problem, Current status: complete.
My main aim from this phase was to define why we were encountering this
problem and in what direction we would go in trying to solve it. I felt the
most important thing at this stage was to ensure I had commitment from core
team members from various functional areas. As there is a 2 shift cycle system
in place for compression I knew that I would not always be present for the
entire duration of the full clean which I felt was not ideal as I was cautious
that accurate cleaning times may not have been recorded. As this gained a lot
of interest from both shift cycles I thought it was essential that I had a
member of both shifts to ensure that recordings were completed correctly.
Brainstorming sessions were also held with both shifts to help define why we
were encountering the problem and what direction we should take. I found the
brainstorming very productive as did the other
members as it included all employees that will be involved in this
project.
The purpose of the
Define phase is to validate the project charter.
Deliverables:
q Project Charter
q Project Benefits
q Team
q Stakeholders
q Benchmarking
q High Level Process Map
q VOC/VOB and CTQs
q Communication Plan
q Project Plan
I found using the
Gantt chart a very useful tool. As it was my first time using this type of
chart I was using it with little confidence at the beginning. But as with
everything in time I grew with confidence. It is a great indicator for showing
progress made and will be a great aid in ensuring project timelines are met. I used the Gantt chart to keep progress on the deliverables from the progress charter.
Gantt charts are also used within the company as a time guideline for each
product campaign, I always found it easy on the eye and a very effective
graph.
All my goals were met in the define stage and on time. I have gathered a keen core team and a very helpful blackbelt sponsor in Jason Flanagan, I am still in the early stages of my project but I look forward to working on the rest of the stages in DMAIC.
All my goals were met in the define stage and on time. I have gathered a keen core team and a very helpful blackbelt sponsor in Jason Flanagan, I am still in the early stages of my project but I look forward to working on the rest of the stages in DMAIC.